from 23.01 to 26.01 we have been in Munich for the scheduled Bench Test, at this test the rocket is beeing assembled but not started. This is to see if all experiments work nominal in near flight conditions. Day 1 consistet of the assembly of our experiment and quick...Dec 10, 2017 | Hardware Design, Mechanical Design, Milestones, NEWS, Project Managment, Software Design, Telemetry Design
A long time has passed since the last post here on our website. The last time required all our time and concentration, in addition to the study, every free minute of the entire team was used for the production.But it was a long way in the last six months. From...Aug 8, 2017 | Milestones, NEWS, Software Design, Telemetry Design
Today the software and telemetry team has performed the range test. Strategic points in the area of Würzburg have been approached, which have a direct visual connection to the university library. The Dummy Seeds, which consist of an Arduino, a Wireless SD Shield as...Jul 16, 2017 | Hardware Design, NEWS, Telemetry Design
We can finally present the hardware configuration for our telemetry system. After many problems with the antennas and some different configuration ideas we decided to use a hardware configuration with two separated helix antennas and one dipole quarter-wave for the...Dec 19, 2016 | NEWS, Telemetry Design
To evaluate the experiment while it is performing and to present some data live, we need an interface to transmit this data to the ground station. We have primarily decided on an already existing commercial satellite communication network (e.g. GlobalStar or Iridium)...